The new rule shifts away from the previous “first filed, first approved” process to a “first ready, first served” approach. The rule also sets firm deadlines for regional transmission organizations and other transmission providers to complete interconnection studies, according to Kessler. Speed up interconnection queue processingThe final rule imposes firm deadlines and establishes penalties if transmission providers fail to complete interconnection studies on time, but transmission providers may appeal their penalties at the Commission. The final rule allows interconnection customers to add a generating facility to an existing interconnection request under certain circumstances without such a request being automatically deemed a material modification. The final rule requires transmission providers to use operating assumptions in interconnection studies that reflect the proposed charging behavior of electric storage resources.